Maintenance
DataCenter Migration
Resolved Jan 30 at 01:00pm CET
As the maintenance concludes, we’ve identified that some customers are still experiencing issues. If you’re encountering any problems, please submit a ticket so we can resolve them as quickly as possible.
DataCenter Migration
Resolved Jan 30 at 12:00am CET
To accommodate our growing customer base and optimize our operations, we will be migrating our main data center in Amsterdam from Equinix AM5 to Digital Realty AMS5. This move is necessitated by the limitations of Equinix AM5, such as restricted space and power capacity.
During the maintenance window, services in Amsterdam will be completely unreachable (as part of the migration). We are working diligently to minimize any downtime and will provide updates throughout the migration process t...
Issue network
Resolved Jan 16 at 08:39am CET
We have successfully implemented a permanent solution to resolve the issue.
Thank you for your patience and understanding throughout this process.
1 previous update